Azikel Power is a pioneer Private Power Plant Project in Bayelsa State with a size and design of 500MW and Simple and Combined-cycle combustion turbine respectively. Being a private pioneer in this venture in Bayelsa State is associated with its peculiar challenges. Azikel Power has since broken the ground with landmark completion of milestones. They are to wit:

  • Power plant site size of 80 acre of land have been procured at Gbarain, Near Yenagoa, Bayelsa State.
  • Plant site clearing completed.
  • ESIA approval has been obtained form the Federal Ministry of Environment
  • Power evacuation studies have been completed and provisional approval granted by the Transmission Company of Nigeria (TCN).
  • Power plant site size of 80 acre of land have been procured at Gbarain, Near Yenagoa, Bayelsa State.
  • Plant site clearing completed.
  • ESIA approval has been obtained form the Federal Ministry of Environment
  • Power evacuation studies have been completed and provisional approval granted by the Transmission Company of Nigeria (TCN).
  • ite Survey, Topographic, Bathymetric (Nun River), Geotechnical, GIS Mapping, Noise & Gaseous Emission Modeling have all been completed.
  • Project Technical Consultant and Owner’s Engineer, “ENERGOPROJEKT-KATOWICE” SA from Poland has been recruited from a competitive process.
  • Collaboration Agreement executed with GE with a proviso for Equity Investment by GE
  • Choice of Technology and Systems from GE
  • Land title (Certificate of Occupancy) perfected
  • Power Generation License obtained from Nigerian Electricity Regulation Commission
  • Technical specification documents that would lead to the selection of EPC and O&M finalized by EPK of Poland. Companies that responded to the EOI for EPC evaluated.
  • Engagement with the Gas Aggregator Company of Nigeria (GACN) is at advanced stage. Response to GACN due diligence documentation submitted.
  • Engagement with SHELL Petroleum Development Company is at advanced stage.
  • PPA – Preliminary discussions held with NBET
  • Registration of the project under the Power Africa Initiated.